Case study
Paver Entry Steps, Wood Wall and New Front Yard in San Carlos
A San Carlos front yard rebuilt with new Belgard paver steps and walk, a capped wood wall along the street, a river rock strip, 200 sq ft of turf, 17 lights and 77 new plants and trees.

- Location
- San Carlos
- Scope
- Artificial Turf
- Completed
- October 2026
- Project size
- 560
- Investment
- $56,500–$66,400
Full project details
- Timeline
- Sold July 3, 2026. Build ran August 19 to September 6, 2026 (19 calendar days), with one approved change order. Project closed out October 26, 2026.
The challenge
Before the project, the front yard of this San Carlos house was bare, dry soil around a curved concrete walk, held at the street by an old wood board wall.
The scope rebuilt the whole front: new paver entry steps and walk, new sections, a cap and sealer on the street-side wall, a river rock strip and a drain line, new planting on irrigation, a small turf lawn around the tree, stepping pads and low-voltage lighting.
Our approach
Sequoia Outdoor removed 6 in. of soil across 1,400 sq ft of yard and ran 46 ln ft of perforated drain pipe to a pop-up emitter, with two downspout connections. The entry got new steps: 140 sq ft of Belgard Catalina Grana pavers with 35 ln ft of Belgard bullnose treads on a concrete step foundation, and an 80 sq ft concrete slab was poured. Along the street, 23 sq ft of new 2x12 wood retaining wall went in, the wall was capped with 60 ln ft of redwood, and 210 sq ft of it was sealed. 160 sq ft of 1 to 2 in. Lynn Creek rock went in over weed cloth, and fifteen Belgard Dimensions 24x24 pads make a stepping path. 70 one-gallon and 6 fifteen-gallon plants and a 24 in. box tree went in under 1,400 sq ft of brown mini bark, on two new irrigation valve zones. 200 sq ft of So Natural 95 turf over gopher wire rings the tree, edged in black steel, and 8 brass path lights, 6 ledge lights and 3 up lights run on a 150 W transformer with a timer.The outcome
The front yard is now planted beds in brown bark with a small turf lawn around the tree, new paver steps and a curved paver walk to the door, a stepping path, and a black capped wall along the street with a rock strip below it. The build ran August 19 to September 6, 2026, and the project closed out October 26.Build highlights

The street-side wall
23 sq ft of new 2x12 wood wall, a 60 ln ft redwood cap and 210 sq ft of sealer, with 1 to 2 in. Lynn Creek rock along the curb.

A stepping path
Fifteen Belgard Dimensions 24x24 pads cross the planting, lit by path lights.

Turf around the tree
200 sq ft of So Natural 95 turf over gopher wire rings the tree, edged in black steel.

A curved paver walk
The new paver walk curves from the entry steps through the new planting.